Susitna-Watana dam studies resume after freeze lifted

Work is resuming on the Susitna-Watana hydroelectric project under spending guidelines put in place by Gov. Bill Walker’s administration.

The overall cost for the proposed 705-foot dam in the upper reaches of the Susitna River has been pegged at $5.6 billion in 2014 dollars by the Alaska Energy Authority, or AEA.

AEA will need $105 million, maybe more, to get through the Federal Energy Regulatory Commission licensing process and to construction, authority Executive Director Sara Fisher-Goad said during an Aug. 6 board meeting. 

However, AEA only has the ability to spend the $6.6 million it has in the bank for the project through 2017. That money should get the project to the study plan determination, at which point FERC would rule whether or not the authority has gathered sufficient relevant data to apply for a project license. The FERC license is the last and largest pre-construction hurdle.

Fisher-Goad said AEA will continue to update data with field studies as necessary to prevent work from becoming stale or outdated.

National Marine Fisheries Service officials have questioned the validity of some Susitna-Watana fisheries studies.

“The longer we stretch this out, we’re losing our economy of scale to be able to have logistics support on several studies at one time,” she said. “We’re doing this in more of an incremental fashion.”

AEA has completed 14 of 58 FERC-approved studies so far, according to AEA Project Manager Wayne Dyok. To date, the project has received $192 million in state appropriations. The Walker administration lifted an administrative order July 6 that halted spending on the dam.

To date, the project has received $192 million in state appropriations. The Walker administration lifted an administrative order July 6 that halted spending on the dam, one of six large infrastructure projects that were put on hold in late December.

After 2017, once AEA has exhausted its funds for working towards a study plan determination, “the project will be revisited in the context of the fiscal environment and other competing major capital projects,” Office of Management and Budget Director Pat Pitney wrote in a memo to Fisher-Goad.

Mike Wood, president of the lead Susitna-Watana opposition group the Susitna River Coalition, in a July 16 release, called resuming the project a “slap in the face” to Alaskans as state leaders discuss ways to increase state revenue during a time of multi-billion dollar budget deficits.

“The proposed dam has already wasted hundreds of millions of state dollars and needs to be immediately shut down,” Wood said. “It diverts necessary funds for other, more responsible and reasonable alternative energy developments, as well as goes against Walker’s campaign promises of fiscal responsibility and fish-first policies.”

AEA has touted the dam, which would generate about 2,800 gigawatts, as a way to provide half of the Railbelt’s energy demand with clean energy at long-term stable prices.

Continuing at a slower pace to prevent unnecessary spending could end up costing the state if the dam is ultimately built, Dyok said at the AEA board meeting.

At $5.6 billion to build today, inflation on project financing could add up to $150 million to the cost each year construction is delayed, he said.

If everything goes according to the current plan, AEA will be able to submit its license application with FERC in 2019, and hopefully begin construction soon after a typical two-year review, according to Dyok. However, if AEA gets the $100 million-plus it needs to submit its application before 2017, that timeline could be accelerated by two years and potentially save the state $300 million.